试题查看
首页
>
PMP考试
> 试题查看
【单选题】
In crashing a task, you would focus on:
A As many tasks as possible.
B Non critical tasks.
C Accelerating performance of tasks on critical path.
D Accelerate performance by minimizing cost.
E A and D.
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
62%
的考友答对了
你可能感兴趣的试题
提供最早/最迟开始和结束日期的工具是什么?
A(n)_____isdefinedasaspecifiedaccomplish
Whichofthefollowingimpactsthecriticalpat
Therangeoftimeallowedforanactivitytobeco
Freefloatistheamountoftimethatanactivity
UsingtheproblemstatedintheSpecialwindow,