【单选题】

In crashing a task, you would focus on:

A As many tasks as possible.
B Non critical tasks.
C Accelerating performance of tasks on critical path.
D Accelerate performance by minimizing cost.
E A and D.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...