试题查看

首页 > PMP考试 > 试题查看
【单选题】

On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:

A ¥-100
B ¥100
C ¥-150
D ¥150
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

85%的考友答对了

你可能感兴趣的试题

AllofthefollowingarecategoriesofamilestoTheactualconfigurationofaPERT/CPMnetworkExcessiveflexibilityinspecifyingrequiremThekeypurposeofprojectcontrolisto:APlanaFasttrackingmeansto:ASpeedupaprojectthroAsaprojectiscarriedoutandslacktimeiscons