试题查看

首页 > PMP考试 > 试题查看
【单选题】

During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule: 

A Now becomes the new schedule, including the changes, and the original baseline is disregarded. 
B Is still the original baseline but annotated to reflect that a change has taken place. 
C Is amended to reflect the scope change, but the original baseline is still maintained for post-project review. 
D Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.) 
E Is the same since baseline schedules cannot change once the development phase is completed.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

89%的考友答对了

你可能感兴趣的试题

UsingthedatashownintheSpecialwindow,ActiUsingthefigureintheSpecialwindow,ByhowmaUsingthefigureintheSpecialwindow,ThecritThefirststepinbuildingaPERT/CPMnetworkisThecriticalpathinaschedulenetworkisthepaAssumethatyouhaveanetworkwhereanactivity