试题查看
首页
>
PMP考试
> 试题查看
【单选题】
Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?
A P
B Q
C R
D S
E T
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
67%
的考友答对了
你可能感兴趣的试题
Resourcelevelingwilloftenaffecttheprojec
UsingthefigureintheSpecialwindow,Theslac
UsingthefigureintheSpecialwindow,Activit
UsingthefigureintheSpecialwindow,Activit
UsingthefigureintheSpecialwindow,TheCrit
对不可再生资源应在符合规划的前提下,实行有序开采,避免开采过度,这符合资源利用的