【单选题】
Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:
A The project manager and project office personnel.
B The project team and functional managers.
C The project sponsor.
D All of the above.
E A and B only.
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...