试题查看

首页 > PMP考试 > 试题查看
【单选题】

a variance envelope has been established on a project. the envelope goes from +-30% in r&d to +-5% during manufacturing. the reason for

the change in thickness of the envelope is because:
a. the management reserve has been used up.
b. the accuracy of the estimates in manufacturing are worse than the estimates in r & d.
c. tighter controls are always needed as a project begins to wind down.
d. of the personal desires of the project sponsor.
e. of none of the above
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

62%的考友答对了

你可能感兴趣的试题

acomprehensivedefinitionofscopemanagemencostpluspercentageofcostcontractsaremorequalitymanagement:a.isanothernameforcare在窗体中有一个命令按钮command1,编写事件代码如下:PrivateSubC已经建立了包含“姓名”、“性别”,“系别”、“职称”等字段的tEmployee表riskmanagementallowstheprojectmanagerand