【单选题】

otal project risk:

a. should not be calculated for small projects
b. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the
project.
c. is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.
d. a and b
e. a and c