【单选题】

The monthly report to the client shows zero schedule variance. However, members of the team know that a milestone has been missed that will cause an overall delay to the project. Which one of the following is being inadequately reported?

A.Communication plan variance 
B.Resource management plan
C.Critical path status
D.Risk analysis
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

12%的考友选择了A选项

2%的考友选择了B选项

73%的考友选择了C选项

13%的考友选择了D选项