To  increase  the  probability  of  obtaining qualified  people  from  a  consultant,  the  project manager should:

A.Include key personnel requirements in the request for proposal
B.Define the statement of work and team structure
C.Hire a large company that has experience with the type of project
D.Require candidates to work on-site for a one-week probationary period
查看答案解析

参考答案: