【单选题】
In your project,you can use all the following tools and techniques for risk response planning EXCEPT______.
A.strategies for negative risks or threats
B.contingent response planning
C.strategy for threat and opportunities
D.strategy for residual risks
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
1%的考友选择了A选项
37%的考友选择了B选项
2%的考友选择了C选项
60%的考友选择了D选项