【单选题】
Risk response development is intended to______.
A.create steps to identify project risks
B.formulate strategies for dealing with adverse events
C.construct a list of previous project risks
D.develop measurements to quantify project risks
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
5%的考友选择了A选项
79%的考友选择了B选项
10%的考友选择了C选项
6%的考友选择了D选项