【单选题】
As a project manager, you examine project results over time to determine how project is performing over time. This can be done through ______ .
A、performance reviews
B、variance analysis
C、trend analysis
D、earned value management
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
0%的考友选择了A选项
12%的考友选择了B选项
86%的考友选择了C选项
2%的考友选择了D选项