As a project manager, you examine project results over time to determine how project is performing over time. This can be done through ______ .

A、performance reviews
B、variance analysis
C、trend analysis
D、earned value management
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

0%的考友选择了A选项

12%的考友选择了B选项

86%的考友选择了C选项

2%的考友选择了D选项