You are the project manager of a civil construction company involved with building houses. In your project, you often use work breakdown structures (WBS)from your previous projects as templates.

A、work breakdown structure can be used for all the following except ______ .
A、tracking project performance against cost and schedule
B、creating a network diagram, with task dependencies
C、creating a project schedule
D、assigning resources to work on different work elements
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

9%的考友选择了A选项

83%的考友选择了B选项

6%的考友选择了C选项

2%的考友选择了D选项