【单选题】

The work breakdown structure is an excellent tool for objective control and evaluation. Which of the following is generally not validated through the WBS

A、Time, schedule, and cost.
B、Management coordination and organizational structuring.
C、Risk and impact of decision—making.
D、Quality of the work.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

24%的考友选择了A选项

2%的考友选择了B选项

1%的考友选择了C选项

73%的考友选择了D选项