A、project team has been arguing for days about the correct way to complete a high level design. This has caused the SPI to fail to 0.89 and has aCPI of 0.9. If the project manager tees the team “we will schedule this discussion for our team meeting next week”. The project manager is ______ .

A、using earned value

B.compromising

C.increase costs even further

D.withdrawing

查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

14%的考友选择了A选项

13%的考友选择了B选项

4%的考友选择了C选项

69%的考友选择了D选项