【单选题】

You are responsible for a systems integration project in your organization that has multiple internal customers.You have just begun preparing a project plan.Because many people in your organization are interested in this system and its progress,you decide to prepare a project communications management plan.Your first step in preparing this plan is to______.

A、conduct a stakeholder analysis to assess information needs
B.determine a production schedule to show when each type of communication will be produced
C.describe the information you plan to distribute
D.set up a repository for all project documents so that they will be easily accessible
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

67%的考友选择了A选项

13%的考友选择了B选项

19%的考友选择了C选项

1%的考友选择了D选项