试题查看

首页 > PMP考试 > 试题查看
【单选题】

In a traditionally drawn decision tree,a circle represents______.
A.a chance to which no estimated monetary value can be assigned so that a likely pay-off can not be shown

B.a decision to which no estimated monetary value can be assigned so that a likely pay-off can not be shown
C.a chance to which an estimated monetary value may be assigned to calculate the most likely pay-off
D.a decision to which an estimated monetary value may be assigned to calculate the most likely pay-off
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

11%的考友选择了A选项

33%的考友选择了B选项

53%的考友选择了C选项

3%的考友选择了D选项