【单选题】

Your project is very critical for the company and must be completed within 6 months. The project charter has been signed, but scope statement is not yet prepareD、Management asks you to go ahead with the project without the scope statement being approveD、What should you do(select the best answer)

A、Refuse to work on the project because management is not following standard project management practice
B.Since time is of essence, you should start the project with the inputs from project charte
C.Meet the management and mention the problems you will face without a scope statemen
D.Escalate the issue to the project sponsor and issue a risk mem
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

9%的考友选择了A选项

19%的考友选择了B选项

57%的考友选择了C选项

15%的考友选择了D选项