When checking the calendar of a team member to schedule a meeting,you see she has scheduled a meeting with a key stakeholder that you were not informed of.The BEST approach would be to______.
A.avoid mentioning it to the team member but continue to watch her activities

B.notify your boss about the problem
C.address the concern with the team member's boss
D.address the concern with the team member
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

32%的考友选择了A选项

1%的考友选择了B选项

3%的考友选择了C选项

64%的考友选择了D选项