Earned value techniqueEVT)is a tool and technique to measure project performance. InEVT,BCWP refers to ______ .

A、physical work actually accomplished, including the estimated value of this work
B、physical work scheduled to be performed, including the estimated value of this work
C、actual cost incurred to accomplish the earned value
D、none of the above