【单选题】
An appropriate sequence for risk management activities is______.
A.identify risks,perform qualitative risk analysis,perform quantitative risk analysis,plan risk responses
B.identify risks,risk assessment。and risk planning
C.identify risks,risk mitigation,and risk management
D.identify risks,risk elimination,and risk mitigation
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
74%的考友选择了A选项
16%的考友选择了B选项
6%的考友选择了C选项
4%的考友选择了D选项