【单选题】

Project team

A、has been hired to manage a transportation project very similar to dozens at projects they’ve managed successfully in the past.The team had determined that the probability of achieving project objectives is 94%.The team has determined the size of contingency reserves that may be needeD、These determinations are included in which process
A、Qualitative risk analysi
B.Plan risk response
C.Quantitative risk analysi
D.Risk identificatio