【单选题】

In order to speed up a project,you made a decision to fast-track a phase currently performed with five team members and another one which was planned to begin in four weeks time with another five team members.Which of the following activities should you do first

A、Make sure that all exit criteria of the consecutive phase have been met to ensure the flow of communications in a team situation which is more complex by a factor of 2.
B.Make sure that all entry criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical aptnes
C.Make sure that all exit criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical performanc
D.Restructure your team and delegate tasks in order to ensure the flow of conmunications in a team situation which is more complex by a factor of 4.5.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

37%的考友选择了B选项

5%的考友选择了C选项

56%的考友选择了D选项