【单选题】

All of the following are examples of a source of scope change EXCEPT ______ .
A.a variation in government regulations

B.failure to include a required feature in the design of a telecommunication system
C.discovering a need to engage in bottom-up cost estimating
D.introducing technology that was not available when scope was originally defined
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

10%的考友选择了A选项

25%的考友选择了B选项

58%的考友选择了C选项

7%的考友选择了D选项