【单选题】

An output of scope definition is ______ .
A.work breakdown structure (WB

B.resource breakdown structure (RB
C.project scope statement
D.schedule delays control plan
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

10%的考友选择了A选项

25%的考友选择了B选项

58%的考友选择了C选项

7%的考友选择了D选项