You are a new project manager who has never managed a project before.You have been asked to plan a new project.It would be BEST in this situation to rely on______during planning in order to improve your chance of success.
A.your intuition and training

B.stakeholder analysis
C.historical information
D.configuration management
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

0%的考友选择了A选项

9%的考友选择了B选项

85%的考友选择了C选项