During activity sequencing,you identify and document interactivity dependencies.All the following are outputs from activity sequencing process EXCEPT______.
A.project schedule network diagrams

B.activity attribute updates
C.requested changes
D.milestone list
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

8%的考友选择了A选项

12%的考友选择了B选项

21%的考友选择了C选项

59%的考友选择了D选项