【单选题】

You have been working on a very large software development project that has made use of over 230 people.Finally,all the scope of work is completed,it would be BEST to______.
A.throw a party for the team members

B.make sure the project is integrated with other projects
C.begin to focus on your other projects
D.analyze project success or failure
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

6%的考友选择了A选项

1%的考友选择了B选项

14%的考友选择了C选项

79%的考友选择了D选项