A project manager learns that corrective action was implemented by a team member,but not documented.What should the project manager do NEXT
A.Report the violation to the functional manage

B.Clarify the reasoning behind the team member's actio
C.Add the implemented corrective action to the historical recor
D.Find out who caused the proble
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

0%的考友选择了A选项

18%的考友选择了B选项

62%的考友选择了C选项

20%的考友选择了D选项