For an activity,the optimistic,most likely and pessimistic estimates are 12,16 and 18 respectively.Which of the following statement is correct
A.There is 68.26% chance that the activity will be completed in 15 to 17 day

B.There is 95.44% chance that the activity will be completed in 15 to 17 day
C.There is 68.26% chance that the activity will be completed in 14.67 to 16.67 day
D.There is 93.73% chance that the activity will be completed in 15 to 17 day
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

9%的考友选择了B选项

88%的考友选择了C选项

1%的考友选择了D选项