【单选题】

The following information is available about a particular task in your project plan:early start(ES),25 days;late start(LS),30 days;early finish(EF),50 days;late finish(LF),55 days.Based on this information。you can deduce that______.
A.the project float is 5 days

B.the project may get delayed
C.the task is not on the critical path
D.the task is on the critical path