【单选题】

Which of the following is a common characteristic of most project life cycle descriptions
A.Cost and staffing are low at start,higher towards the end of implementatioand drop rapidly as the project nears completio

B.The probability of successfully completing the project is highest at the start of the projec
C.Stakeholders have the most influence on the final characteristics of the product at the end of the projec
D.Risk and uncertainty are lowest at the start of the projec
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

67%的考友选择了A选项

18%的考友选择了B选项

13%的考友选择了C选项

2%的考友选择了D选项