试题查看

首页 > PMP考试 > 试题查看
【单选题】

Which process group focuses on completing the requirements of the project
A.Initiatin

B.Plannin
C.Executin
D.Closin
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

4%的考友选择了A选项

16%的考友选择了B选项

75%的考友选择了C选项

5%的考友选择了D选项

你可能感兴趣的试题

IncaseofconflictsofinterestamongstakeholWhichofthefollowingisacommoncharacteristRequirementsdocumentationisaninputto____ThefollowinginformationisavailableaboutaWhichofthefollowingstatementiswrongA.LeaWhatissometimesreferredtoasglobalilliter