【单选题】

The method of analyzing the sequence of activities with the least amount of scheduling flexibility to control the schedule is called______.
A.flowchart

B.critical path
C.work breakdown structure
D.precedence diagramming
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

4%的考友选择了A选项

72%的考友选择了B选项

14%的考友选择了C选项

10%的考友选择了D选项