【单选题】

You are looking at the following data.Project A has a CPI of 0.8 and SPI of 1.2 and EV of 450.Project B has CPI of 1.2 and SPI of 0.8 and EV of 650.Which of the following statement is true
A.Project B is performing better because it has a higher earned valu

B.Project A has schedule slippage and project B is ahead of schedul
C.Crashing project A is a good optio
D.Crashing project B is a good optio