The project manager can enhance project communications and team building by doing all the following except______.
A.having a“war room”

B.being a good communication blocker
C.being a communication expeditor
D.holding effective meetings
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

如答案有误或试题有侵权,请联系我们。[提交反馈][在线客服]

根据网考网移动考试中心的统计,该试题:

36%的考友选择了A选项

63%的考友选择了B选项

0%的考友选择了C选项

1%的考友选择了D选项