【单选题】

You prepared an integrated project plan and a project schedule.You submitted it to the steering committee,and it was approved.Key stakeholders accepted the plan.It is time to distribute it.Both the project plan and schedule should be distributed to______.
A.all stakeholders in the performing organization

B.all project stakeholders
C.project team members and the project sponsor
D.people noted in the communications management plan