You have created the project charter but could not get it approved. Your manager and his boss asked that the project begin immediately. Which of the following is the BEST thing to do
A.Set up an integrated change control proces

B.Push to get the charter signe
C.Perform an impact analysi
D.Start work on only the critical path task
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

4%的考友选择了A选项

87%的考友选择了B选项

8%的考友选择了C选项

1%的考友选择了D选项