【单选题】

All of the following are characteristics of the project management information system(PMIS)EXCEPT:
A.It is a standardized set of automated tools available within the organization and integrated into a syste

B.It is used by the project management team to support generation of the project management plan, facilitate feedback as the document is developed, control changes to the project management plan, and release the approved documen
C.It is used by the project management team to monitor and control the execution of activities that are planned and scheduled in the project, management pla The PMIS is also used to create new forecasts as neede
D.It is used by the project management team primarily to generate presentations to key stakeholder Typically, a separate, manual system is used for the integrated change control process, to facilitate feedback and control changes across the projec
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

17%的考友选择了B选项

5%的考友选择了C选项

76%的考友选择了D选项