During initiation, a project manager is planning the upcoming project execution team meetings. What should the project manager include in these meetings that would have the biggest impact on the project
A.Review of the action item lis

B.Review of identified risk
C.Assignment of tasks to team member
D.Estimating cost
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

1%的考友选择了A选项

62%的考友选择了B选项

3%的考友选择了C选项

34%的考友选择了D选项