【单选题】

A project should be terminated for all of the following reasons EXCEPT:
A.Lack of team synerg

B.The project no longer meets the company's objective
C.The resources are not available to complete project activitie
D.Project funding has been significantly reduce
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

67%的考友选择了A选项

7%的考友选择了B选项

16%的考友选择了C选项

10%的考友选择了D选项