【单选题】

Puts into overall Change control include all of the following EXCEPT______.
A.project management plan

B.change requests
C.change control meetings
D.work performance information
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

1%的考友选择了A选项

25%的考友选择了B选项

60%的考友选择了C选项

14%的考友选择了D选项