【单选题】

All the following are advantages of GERT(graphical evaluation and review techniques)as compared with PERT(project evaluation and review technique)EXCEPT ______ .
A.allows looping

B.allows for dummy tasks
C.allows branching
D.allows multiple project end results
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

30%的考友选择了A选项

62%的考友选择了B选项

4%的考友选择了C选项

4%的考友选择了D选项