【单选题】

Your schedule analysis has shown that your project has a high likelihood of experiencing a schedule overrun. You know this because the cumulative EV is much ______ .
A.higher than the cumulative AC

B.higher than the cumulative PV
C.lower than the cumulative PV
D.lower than the cumulative CPI
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

4%的考友选择了A选项

30%的考友选择了B选项

62%的考友选择了C选项

4%的考友选择了D选项