【单选题】

Management of the project team is complicated ______ .
A.when team members are co-located

B.when minor problems do not impact the project completion date OE budget target
C.when team members are accountable to both a functional manager and the project manager
D.when formal training plans are implemented
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

2%的考友选择了A选项

29%的考友选择了B选项

54%的考友选择了C选项

15%的考友选择了D选项