试题查看
首页
>
PMP考试
> 试题查看
【单选题】
Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A 2
B 3
C 4
D 5
E 7
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...
根据网考网移动考试中心的统计,该试题:
59%
的考友答对了
你可能感兴趣的试题
Thekeypurposeofprojectcontrolisto:APlana
Fasttrackingmeansto:ASpeedupaprojectthro
Asaprojectiscarriedoutandslacktimeiscons
Thepurposeofadummyactivityinanactivity-o
OnNovember1,$1000worthofworkontaskAwassu
Aplanhasbudgetedthreeweeksofeffortforcon