试题查看

首页 > PMP考试 > 试题查看
【单选题】

Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.

A 2, 10
B 4, 12
C 6, 14
D 7, 15
E 9, 17
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

52%的考友答对了

你可能感兴趣的试题

Fasttrackingmeansto:ASpeedupaprojectthroAsaprojectiscarriedoutandslacktimeisconsThepurposeofadummyactivityinanactivity-oOnNovember1,$1000worthofworkontaskAwassuAplanhasbudgetedthreeweeksofeffortforconResourcelevelingwilloftenaffecttheprojec