A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:
A 4 weeks B 5 weeks C 6 weeks D 7 weeks E None of the above.