试题查看

首页 > PMP考试 > 试题查看
【单选题】

A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be: 

A 4 weeks 
B 5 weeks 
C 6 weeks 
D 7 weeks 
E None of the above.
查看答案解析

参考答案:

正在加载...

答案解析

正在加载...

根据网考网移动考试中心的统计,该试题:

82%的考友答对了

你可能感兴趣的试题

ThecriticalpathinaschedulenetworkisthepaAssumethatyouhaveanetworkwhereanactivityYourteamhaspreparedaCPMscheduleforyourreDuringprojectexecution,thecustomerauthorNetworkschedulesarepreparedduringthe____SchedulingsystemssuchasPERT,ADM,andPDMar