Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:
A All activities. B Only those activities with the longest time durations. C Those activities on the critical path begining with the longest time duration activities. D Those activities with the greatest degree of risk. E None of the above.