【单选题】

Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to: 

A All activities. 
B Only those activities with the longest time durations. 
C Those activities on the critical path begining with the longest time duration activities. 
D Those activities with the greatest degree of risk. 
E None of the above.