【单选题】
ADM is an activity-on-arrow method. In this method, a dummy activity:
A Denotes a critical path relationship.
B Denotes any dependency relationship.
C Shows slack.
D Identifies customer deliverables dates.
E Identifies customer team meeting dates.
查看答案解析
参考答案:
正在加载...
答案解析
正在加载...